Free Benefits Tracking Tool

See whether your improvement projects are delivering the savings they promised: plan versus realised by month, a year-end forecast, and which projects need help.

  • 100% free
  • No sign-up
  • Export to PDF, PNG & Excel
  • Data stays in your browser
Realised to date$578k
Of plan to date93%
Validated$395k
Year-end forecast$745k
Plan for the year$803k

The portfolio has realised $578,000, 93% of the $622,500 planned to the end of Oct. At the current rate it will reach about $745k by year end, against a plan of $803k.

✗ Off track (below 70% of plan): SMED on packaging line (56%).

⚠ At risk (70–90%): Batch record errors (DMAIC) (89%).

Only $395k (68%) of the realised benefit is validated by finance.

Click a project to set its planned benefit, start month and type. Enter the realised benefit per month in the table below. The black tick on each bar is the plan to date. + adds a project.

Planned (cumulative)RealisedForecast to year end$0$200k$400k$600k$800k$1MForecastJanFebMarAprMayJunJulAugSepOctNovDecPlan $803kForecast $745k$578k to datePROJECTS: REALISED VS PLANNED, JAN–OCTHard savingsCost avoidanceRevenueSoft / capacityScrap reduction on line 3$205k / $200kValidated✓ 103%Batch record errors (DMAIC)$107k / $120kValidated⚠ 89%Supplier PPM programme$83k / $90kValidated✓ 92%SMED on packaging line$42k / $75k✗ 56%Faster launch of new SKUs$104k / $100k✓ 104%Lab review by exception$37k / $37.5k✓ 99%% of plan to date; validated = confirmed by financeAdd a projectAdd a project
Benefits tracking chart: cumulative planned and realised benefits with the year-end forecast, and each project's realised benefit against its plan to date. Select a project to edit it.

Projects

Plan = planned per year ÷ 12 for each month from the start month
ProjectOwnerTypePlanned per yearStartsStatusValidated
✓ 103%
⚠ 89%
✓ 92%
✗ 56%
✓ 104%
✓ 99%

Realised benefit per month ($)

Months after "Actuals up to" are ignored
ProjectJanFebMarAprMayJunJulAugSepOctNovDec
Scrap reduction on line 3
Batch record errors (DMAIC)
Supplier PPM programme
SMED on packaging line
Faster launch of new SKUs
Lab review by exception

Benefit types: Hard savings: lower spend that shows in the p&l (less scrap, material, overtime). Cost avoidance: costs that would have been incurred but were prevented. Revenue: extra sales or margin enabled by the improvement. Soft / capacity: freed time or capacity not (yet) converted into cash.

What is benefits tracking?

Improvement projects are approved on the promise of benefits. Benefits tracking checks that promise every month: it compares the benefit each project planned with what it actually realised, adds them up for the portfolio, and forecasts the year end. It tells a steering committee which projects are delivering, which need help, and how much of the reported savings finance has confirmed.

Types of benefit

TypeMeaningExample
Hard savingsLower spend in the P&LLess scrap, material or overtime
Cost avoidanceA cost that would have happened but was preventedFewer deviations, avoided supplier claims
RevenueExtra sales or marginFaster launch, regained customers
Soft / capacityFreed time or capacity, not yet cashAnalyst hours saved by a faster review

Benefits tracking example

A continuous improvement portfolio of six projects has realised $578,000 by the end of October, 93% of the $622,500 planned to date. Four projects are on track, led by scrap reduction on line 3 (103%). The batch record errors project is at risk at 89%, and SMED on the packaging line is off track, with $42,000 against $75,000 planned (56%), so the team reviews its changeover standard. At the current rates the portfolio will reach about $745,000 by year end against a plan of $802,500. Only $395,000 of the realised benefit is validated by finance; the other projects are scheduled for validation in November.

Tips

  • Agree the baseline and the calculation with finance before the project starts.
  • Separate hard savings from the rest; mixing them undermines trust in the total.
  • Track benefits for 12 months after the project closes; gains that are not sustained are not benefits.
  • Estimate the opportunity first with the cost of poor quality calculator, and prove each gain with a before-and-after analysis.

How to use this Benefits Tracking tool

  1. Set up the portfolio. Name the portfolio, the year, the currency and the last month with actual figures.
  2. Add the projects. Click + or use the table to add each project with its owner, benefit type, planned benefit per year and start month.
  3. Enter the actuals. Enter the realised benefit per project per month in the monthly table.
  4. Mark validated projects. Tick the projects whose benefits finance has validated.
  5. Review. Read the cumulative plan versus realised chart, the year-end forecast and the projects off track.
  6. Export. Export the chart and tables to PDF or Excel for the steering committee.

Frequently asked questions

What is benefits tracking?

Benefits tracking compares the benefits an improvement project promised, such as savings, avoided costs or extra revenue, with what it actually delivers, month by month. It shows whether a portfolio of projects is on track and keeps the reported savings honest.

What types of benefit are there?

Hard savings reduce spending that shows in the profit and loss account (less scrap, material, overtime). Cost avoidance prevents costs that would otherwise have been incurred (a price increase avoided, a recall prevented). Revenue benefits come from extra sales or margin. Soft benefits, such as freed time or capacity, are real but not cash until the time is used.

How is the plan calculated?

Each project has a planned benefit per year once it is fully running and a start month. The plan for each month is the annual benefit divided by 12, from the start month on. Planned to date is the sum up to the latest month with actuals.

How is the year-end forecast calculated?

For each project, the forecast is the benefit realised so far plus the remaining monthly plan, scaled by the project's realisation rate to date (capped at 120%). A project delivering 56% of its plan is assumed to keep delivering 56%.

Why should finance validate benefits?

Improvement teams tend to be optimistic. When finance agrees the baseline, the calculation and the realised amount, the savings can be trusted and counted in budgets. The tool shows how much of the realised benefit is validated.

When is a project on track?

In this tool a project is on track at 90% or more of its plan to date, at risk between 70% and 90%, and off track below 70%. These thresholds are common in portfolio reviews; adjust your actions, not the plan, when a project falls behind.