Free Cycle Time Analysis Tool

Time each work element over several cycles, spot unusual readings and calculate normal and standard time, with a sample-size check and a comparison to takt.

  • 100% free
  • No sign-up
  • Export to PDF, PNG & Excel
  • Data stays in your browser
Observed cycle55.5 s
Normal time56.0 s
Standard time62.7 s
Standard time vs takt104%
Unusual readings1

The standard time of 62.7 s is above the takt time of 60 s. With allowances, this station cannot keep up with demand.

1 unusual reading (dashed red outline in the chart). Check for foreign elements such as a dropped part or an interruption; they are excluded from the means.

6 rows · Tip: copy cells in Excel and paste them into any cell (Ctrl+V). Enter moves down.
#ElementRating %12345678910
1
2
3
4
5
6

Element statistics (seconds)

ElementnMeanMinMaxSDCVRatingNormal timeReadings neededUnusual
Pick housing, place in fixture104.073.804.400.194.6%100%4.074
Insert PCB and drive 4 screws918.2417.5019.000.502.8%105%19.162#7
Connect cable harness109.859.1010.800.525.3%95%9.364
Fit cover and snap106.225.906.600.233.7%100%6.222
Function test (automatic)1012.0512.0012.200.070.6%100%12.051
Label and place on conveyor105.104.705.600.285.5%100%5.105
Pick housing, place in fixtureInsert PCB and drive 4 screwsConnect cable harnessFit cover and snapFunction test (automatic)Label and place on conveyor020406080Seconds per cycle55.2154.4257.2355.2455.8555.2663.5755.8854.7955.710CycleAverage 55.53 sTakt 60 s
Stacked bar chart of observed cycle time per cycle, split by work element, with the average and takt time.

Normal time = mean × rating. Standard time = Σ normal time × (1 + allowance). Readings needed uses n′ = (40·√(nΣx² − (Σx)²) ÷ Σx)².

What is a cycle time study?

A cycle time study (or stopwatch time study) measures how long each part of an operation really takes. Observing several cycles shows not just the average but the variation, which is often the bigger problem: an element that usually takes 18 seconds but sometimes 26 will disrupt flow. The results feed standard work, line balancing, capacity planning and costing.

Time study calculations

StepFormula
Observed time per elementMean of the valid readings
Normal timeObserved time × performance rating
Standard timeΣ normal times × (1 + PF&D allowance)
Readings needed (±5%, 95%)n′ = (40 × √(nΣx² − (Σx)²) ÷ Σx)²
Unusual readingsOutside Q1 − 1.5 IQR or Q3 + 1.5 IQR of the element's readings

Time study example

An industrial engineer times six elements of a controller assembly over ten cycles. One reading of the screw-driving element, 25.6 seconds against a typical 18, is flagged: the operator dropped a screw. Excluding it, the average observed cycle is about 55.5 seconds. With ratings (the screw-driving operator worked at 105%, the cable connection at 95%) and a 12% allowance, the standard time is about 62.7 seconds, above the 60-second takt. The station needs rebalancing or a faster screw-driving method before it can meet demand.

Tips for better time studies

  • Explain why you are there. Time studies are about the process, not the person. Involve the operator.
  • Define break points that can be seen or heard (part placed, tool released) so every reading starts and stops at the same point.
  • Separate manual and machine time. Machine elements barely vary; manual ones do.
  • Note every interruption rather than silently discarding it: abnormal readings show real problems.
  • Study the standard method, or you will time a method that should be changed first. Look for waste.

How to use this Cycle Time Analysis tool

  1. Define the elements. List the work elements of the operation in order, each with a clear start and end point.
  2. Record the observations. Choose the number of cycles and type or paste the observed seconds for each element (copy straight from Excel).
  3. Rate and set allowances. Enter a performance rating for each element and the PF&D allowance for the job.
  4. Review unusual readings. Readings outside the normal spread are flagged; exclude them from the means if they were interruptions.
  5. Check the sample size. The tool shows how many readings each element needs for ±5% precision at 95% confidence.
  6. Get the standard time. Read the normal and standard times, compare them with takt and export the time study to PDF or Excel.

Frequently asked questions

What is cycle time?

Cycle time is how long a process step takes to complete one unit, from the start of one unit to the start of the next. It is measured at the process, usually with a stopwatch time study or from machine data, and compared with takt time, the pace customers require.

How do you do a time study?

Break the operation into work elements with clear start and end points, observe and time each element over several cycles, rate the operator's pace, then calculate the normal time (mean × rating) and add allowances for personal needs, fatigue and delays to get the standard time.

How many cycles should I observe?

Enough to estimate the mean precisely. This tool uses the common formula n′ = (40√(nΣx² − (Σx)²) ÷ Σx)², which gives the number of readings for ±5% precision at 95% confidence. Elements with high variation need more readings; 10 to 20 cycles is typical for short manual work.

What is a performance rating?

A rating adjusts observed times to a normal pace. 100% is normal; an operator working faster than normal is rated above 100% (e.g. 110%), slower below. Rating needs training and is often the least reliable part of a time study, so many companies use pre-determined time systems like MTM for comparison.

What are PF&D allowances?

Personal, fatigue and delay (PF&D) allowances add time for personal needs, recovery from fatigue and unavoidable minor delays. They are expressed as a percentage of normal time, typically 10% to 20% depending on the physical demands and environment.

What is the difference between cycle time, lead time and takt time?

Cycle time is how often a step completes a unit. Lead time is how long one unit takes to travel through the whole process, including waiting. Takt time is the rate the customer requires. Reducing waiting cuts lead time; balancing work cuts cycle time to meet takt.

Free tool

5S Audit

Score Sort, Set in order, Shine, Standardize and Sustain, see the 5S radar and track the findings.

Open tool →
Free tool

Kaizen Report

Document quick improvements on before/after kaizen cards and total the annual savings.

Open tool →
Free tool

Kaizen Event

Plan a kaizen blitz: charter, team, daily agenda, before/after metrics and the 30-day action list.

Open tool →
Free tool

Standard Work

Build a standard work combination sheet with manual, machine and walk time against takt.

Open tool →
Free tool

Takt Time Calculator

Calculate takt time from available time and demand, then compare every step and size the crew.

Open tool →
Free tool

Line Balancing

Balance tasks across stations with precedence, see the Yamazumi chart and balance efficiency.

Open tool →
Free tool

Kanban Calculator

Size kanban loops from demand, lead time and safety stock, then print the kanban cards.

Open tool →
Free tool

Poka-Yoke

Mistake-proof a process: rate each error, design a device and move it up the control hierarchy.

Open tool →
Free tool

SMED

Cut changeover time: split internal and external work, convert and streamline, compare before/after.

Open tool →
Free tool

Heijunka

Level the production mix: build a heijunka box, a mixed-model sequence and check interval load.

Open tool →
Free tool

Visual Management Board

Run a daily SQDCP tier board with letter calendars, KPI status and an action list.

Open tool →
Free tool

Gemba Walk

Walk the floor with a structured checklist, log observations and follow up on the actions.

Open tool →
Free tool

Waste Analysis

Find and cost the 8 wastes (TIMWOODS) and rank where the time and money go.

Open tool →
Free tool

OEE Calculator

Calculate availability, performance, quality and OEE with a six big losses waterfall.

Open tool →
Free tool

Value Stream Mapping

Map material and information flow, calculate takt time, lead time and process cycle efficiency.

Open tool →
Free tool

Spaghetti Diagram

Trace people and material movement on a floor plan and measure the distance travelled.

Open tool →

Make lean improvements stick

Cloudtheapp keeps the new standard in place: digital work instructions and checklists at the station, controlled documents with training records, audits, and every improvement action tracked to closure in one validated cloud platform.