Free SMED Changeover Analysis Tool

List the steps of a changeover, separate internal from external work and plan the improvements, then see how much machine time you win back.

  • 100% free
  • No sign-up
  • Export to PDF, PNG & Excel
  • Data stays in your browser
Changeover now111 min
After SMED31 min
Reduction72%
Machine time freed13.3 h/week
External work after26 min

Savings by improvement type: Streamline 47 min · Convert to external 28 min · Eliminate 5 min. Aim for a single-digit changeover (under 10 minutes) with further streamlining and parallel work.

Click any block to edit an element: mark it internal or external, and choose how to improve it. Blue is done with the machine stopped, green while it runs.

Internal (machine stopped)External (machine running)020406080100120minutesBefore: machine stopped1234567891011111 minBefore: machine runningAfter: machine stopped4568931 minAfter: machine running121026 minChangeover (machine stopped): 111 → 31 min, 72% shorter · 13.3 machine hours freed per week1.Find next die and tools12 min int.→ 10 ext. · Convert2.Bring die to press with forklift8 min int.→ 8 ext. · Convert3.Unbolt old die (8 bolts)10 min int.→ 2 int. · Streamline4.Remove old die6 min int.→ 6 int. · Keep as is5.Clean bolster5 min int.→ 5 int. · Keep as is6.Position and align new die15 min int.→ 4 int. · Streamline7.Bolt new die10 min int.→ 2 int. · Streamline8.Adjust shut height, trial hits20 min int.→ 6 int. · Streamline9.First-piece inspection12 min int.→ 6 int. · Streamline10.Return old die to the rack8 min int.→ 8 ext. · Convert11.Fill in changeover paperwork5 min int.→ eliminatedAdd a changeover element
SMED timeline of the changeover elements, internal and external, before and after improvement. Select an element to edit it.

Changeover elements

#ElementNow (min)Done whileImprovementAfter (min)Idea / how
1
2
3
4
5
6
7
8
9
10
11

What is SMED?

SMED (Single-Minute Exchange of Die), also called quick changeover, is a method to reduce the time a machine stands still between the last good part of one product and the first good part of the next. Shigeo Shingo developed it in the 1950s and 1960s, cutting die changes on large presses from hours to minutes. Short changeovers are the key to small batches, low inventory and levelled production, and they directly raise OEE.

The SMED stages

StageWhat you doTypical gain
0. ObserveRecord the current changeover step by step, with times (video helps)Baseline
1. SeparateIdentify which elements are internal and which can be external30–50%
2. ConvertMove internal work outside the stop: preparation, preheating, stagingFurther 10–30%
3. StreamlineSpeed up what remains: quick clamps, no adjustments, parallel workDown to single minutes
4. StandardizeWrite the new method as standard work and train every teamHolds the gain

SMED example: press die change

A press die change takes 111 minutes with the press stopped. Finding the die and tools, bringing the die to the press and returning the old die can all be done while the press is running (converted to external). Hydraulic quick clamps replace eight bolts, locating pins and standard heights remove most of the alignment and trial hits, a go/no-go gauge speeds up first-piece inspection, and scanning the die in the MES eliminates the paperwork. The machine-stopped time falls to 31 minutes, 72% shorter. With ten changeovers a week, that frees about 13 hours of press time every week.

Practical SMED ideas

  • Prepare everything first: a changeover cart with the die, tools and checklist, ready before the stop.
  • Replace bolts: quick clamps, cam locks, one-turn fasteners or U-slots.
  • Eliminate adjustments: locating pins, standard die heights, preset settings and stops.
  • Work in parallel: two people with a clear sequence often halve internal time.
  • Make it visual: colour-code tools and settings per product; error-proof with poka-yoke.

How to use this SMED tool

  1. Record the changeover. Film or observe a changeover and list every element in order with its duration in minutes.
  2. Separate internal and external. Mark each element as internal (machine stopped) or external (machine running).
  3. Choose improvements. Click an element and choose: convert to external, streamline (with the new time), eliminate or keep.
  4. Compare before and after. The timeline shows the machine-stopped time before and after, with the reduction and the machine hours freed per week.
  5. Record the ideas. Write how each improvement will be made (quick clamps, preset heights, cart, checklist).
  6. Export. Export the SMED analysis to PDF, PNG or Excel for the kaizen event or the changeover standard.

Frequently asked questions

What is SMED?

SMED (Single-Minute Exchange of Die) is a lean method for cutting changeover time, developed by Shigeo Shingo at Toyota. The goal is a changeover in single-digit minutes (under 10). It works by separating internal work (done with the machine stopped) from external work (done while it runs), converting internal work to external, and streamlining everything that remains.

What is the difference between internal and external setup?

Internal setup can only be done when the machine is stopped, such as removing and mounting a die. External setup can be done while the machine is still running the previous job or already running the next, such as fetching tools, preheating the die or filling in paperwork.

What are the steps of SMED?

1 Observe and record the current changeover with times. 2 Separate internal and external elements. 3 Convert internal elements to external where possible. 4 Streamline the remaining internal elements (quick clamps, standard heights, parallel work, no adjustments). 5 Streamline external elements. 6 Standardize the new method and train.

How is changeover time measured?

Changeover time runs from the last good part of the previous product to the first good part of the next one, at full speed. It includes setup, adjustment, trial runs and first-piece inspection, not only the mechanical die change.

What are the benefits of SMED?

Shorter changeovers free machine capacity (higher OEE), allow smaller batches and more frequent changeovers, which cut inventory and lead time and make production levelling (heijunka) possible. They also make changeovers safer and more repeatable.

What are typical SMED improvements?

Preparing tools and the next die before stopping, quick-release clamps instead of bolts, locating pins and standard die heights to remove adjustments, preset settings, intermediate jigs, parallel work by two people, and checklists so nothing is forgotten.

Free tool

5S Audit

Score Sort, Set in order, Shine, Standardize and Sustain, see the 5S radar and track the findings.

Open tool →
Free tool

Kaizen Report

Document quick improvements on before/after kaizen cards and total the annual savings.

Open tool →
Free tool

Kaizen Event

Plan a kaizen blitz: charter, team, daily agenda, before/after metrics and the 30-day action list.

Open tool →
Free tool

Standard Work

Build a standard work combination sheet with manual, machine and walk time against takt.

Open tool →
Free tool

Takt Time Calculator

Calculate takt time from available time and demand, then compare every step and size the crew.

Open tool →
Free tool

Cycle Time Analysis

Run a time study: element statistics, sample size check, rating and allowances to standard time.

Open tool →
Free tool

Line Balancing

Balance tasks across stations with precedence, see the Yamazumi chart and balance efficiency.

Open tool →
Free tool

Kanban Calculator

Size kanban loops from demand, lead time and safety stock, then print the kanban cards.

Open tool →
Free tool

Poka-Yoke

Mistake-proof a process: rate each error, design a device and move it up the control hierarchy.

Open tool →
Free tool

Heijunka

Level the production mix: build a heijunka box, a mixed-model sequence and check interval load.

Open tool →
Free tool

Visual Management Board

Run a daily SQDCP tier board with letter calendars, KPI status and an action list.

Open tool →
Free tool

Gemba Walk

Walk the floor with a structured checklist, log observations and follow up on the actions.

Open tool →
Free tool

Waste Analysis

Find and cost the 8 wastes (TIMWOODS) and rank where the time and money go.

Open tool →
Free tool

OEE Calculator

Calculate availability, performance, quality and OEE with a six big losses waterfall.

Open tool →
Free tool

Value Stream Mapping

Map material and information flow, calculate takt time, lead time and process cycle efficiency.

Open tool →
Free tool

Spaghetti Diagram

Trace people and material movement on a floor plan and measure the distance travelled.

Open tool →

Make lean improvements stick

Cloudtheapp keeps the new standard in place: digital work instructions and checklists at the station, controlled documents with training records, audits, and every improvement action tracked to closure in one validated cloud platform.